Case Study
Spares Optimisation
Spares Optimisation
Client’s Issue
Spares not available for key breakdowns, large proportion of spares with no recorded movements in three years
MRO Insyte’s solution
Working with production and maintenance teams MRO Insyte concentrated on regular and high downtime cost failures, conducting failure mode and effects analysis (FMEA) and after working through ways of mitigating the current failures MRO Insyte highlighted the spares required to ensure downtime was minimised. Spares with no recorded movements were analysed and a Bill of Materials (BoM) programme put in place (see bill of materials case study)
Impact on client’s business
Reduction of over 50% in recorded costs of downtime